Town of Palm Beach Marina Construction remains on schedule with the following highlights for the month of March:
Marina excavation and fill disposal at Tarpon Cove is ongoing – over 330 loads of material have been transported via barge to the site.
Brazilian building which will house the marina main office, dock master’s office, and marine unit office is well underway! Windows were installed the week of March
Deadman anchor installation continues and is almost to the Peruvian dock.
Concrete cap and facing continues as it nears its termination point just south of the Peruvian Dock.
Australian Building is progressing nicely – block walls are now in place with window installation ongoing.
Bellingham Dock Manufacturing at Jacksonville Plant is going on schedule – Australian dock now being delivered and assembled
Palm Way dock utilities is ongoing
Brazilian dock utilities ongoing
Upland electrical conduit is continuing
D6 Building electrical work has been started
D6 Building modifications are in progress
Wilco/FPL upland work has begun
Upland water and sewer is nearly finished, other than the Peruvian